The Gascoigne Wood South Spine Tunnel was a very new concept in coal mining roadway development. A Thyssen 12-35 FLP Tunnel Boring Machine had been trialled in an 476m overburden undersea heading development at Dawdon Colliery starting in 1975 with varying success. The heading was a 3.6 m circular tunnel driven through coal measures in mudstones and fine sandstones with broken zones of coal, shalestone and seatearth. The machine progressed 1086m in 1975 but gradually proved to be unsuccesful completing only 1398m by 1978 when it was abandoned.
The Robbins 193-214 TBM was designed to fulfill the high speed drivage required for the development of the Selby Complex coal clearance tunnels exiting at Gascoigne Wood Drift. It was a 5.8m diameter TBM designed to have advance rates of over 120m per week.

The Robbins TBM Erection Chamber.

The cutting head consist of a disc cutter rotating at five revolutions per minute scooping heading material onto a rear facing conveyor. The cutter head, which contains 42 roller cutters, is designed so that they can be changed from inside the head at the rear of the face for safety.

This picture gives you an idea of the sheer size of this machine and the size of the erection chamber required to build it which was 40m long and over 8.5m high. The T.B.M. was designed and built at the Robbins factory in Seattle, U.S.A. The T.B.M. was tested and then shipped to the Gascoigne Wood Mine erection chamber for the build up and testing before being accepted for use underground. The T.B.M. cut a 5.8 metre circular tunnel, then a 5 piece circular girder was installed at 1m centres. The heading roadway, behind the machine, was then backfilled, using the cutter muck, up to 1.2m. The conveyor running through the machine had a controllable delivery point, to deliver the muck, into the roadway at the back of the machine. This created a flat base, in the circular roadway, to allow for services such as the conveyor to deliver development muck to the surface and rails to be installed for the supplies to the heading.

The Robbins Miner.
The 240 tonne 193-214 T.B.M. consisted of seven sections :-
- The Cutter Head,
The cutter head carried the disc cutter and rotated at 5 rpm. It scooped the material, cut at the face, and transferred it via chutes on to the internal machine conveyor. It consisted of 5, large bolted sections. It allowed for changing of the rotating cutters from inside the cutter head structure for safety purposes.
2. Cutterhead Support and Main Beam,
The cutter head shield provided the support for the main bearing mounts, ring gear seals and gear reducers. It transmitted all the cutting and steering torque forces to the main beam. It also provided extending fingers, in the upper section, to the ring beam erection area. The main beam was bolted to the rear of the shield and slid within the gripper section at the rear of the machine. Its main function was to transmit forces to the main gripper assembly and also housed the machine conveyor.
3. Gripper and Propel,
The gripper assembly comprised of the gripper shoes, cylinder, gripper carrier, torque and propel cylinders. During cutting operations the gripper shoes were held against the tunnel wall whilst the propel cylinders pushed the machine forward against the gripper assembly. This allowed the machine to be steered.
4. Machine Conveyor,
The hydraulic machine conveyor was situated inside the main beam and delivered the heading material to the main clearance conveyor or the heading backfill facility.
5. Rear Support,
The two legs and shoes operated by 2 hydraulic rams which support the machine during the regripping phase.
6. Ring Beam Erector,
This section erected the 5 piece rings girders within 2 metres of the face. It was positioned under the cutter shield fingers
7. Pantechnicon,
This section was supported by a twin monorail system. It carried all the support systems for the T.B.M. and consisted of :-
a) The 120m overlap dirt disposal conveyor.
b) The 10 sections carrying the electrical equipment including 2 x 6.6kv / 1100v 1.5 MVA transformers and air scrubber fan.
c) The auxiliary fan overlap system for face ventilation including a telescopic sectional system for heading advancement.
d) Two hoists for unloading heading supplies from minecars.
e) A series of monorail mounted bogies used for carrying the 6.6 kv type 631 electrical supply cables and water hoses allowing a 200m advancement before a move up is required.
The invert fill was was 20m back from the face and did not require any tamping of material.
The materials needed for the heading was transported on an internal monorail system through the body of the T.B.M.
The dust control system was mounted behind the cutterhead and was connected to the dust collection system mounted inside the machine.
All the hydraulic services operated on an N.C.B. standard 40/60 oil/water emulsion to adhere to the fire resistance standards (HFB). These hydraulic system were mainly 2000 psi but some system parts were operating at 3000 psi.
The outbye side of the pantechnicon, mounted over the conveyor, was the 6.6kv GEC MIVAC electrical supply isolation unit.