
Plan of coal faces at Stillingfleet Mine with seven worked in the North Selby Mine area.

The first coal faces at Stillingfleet Mine were worked from the east / west lateral roadways. The first face worked in Jan 1988 was H01Bs on the west side of the mine. H01Cs started production in May 1988 at the east side of the mine. The lateral heading to the east of the mine was the connection with the North Selby Mine lateral roadway called West 2 Conveyor Road and was completed in July 1989. The heading was developed using two Dosco Mk 3 roadheaders. The roadway was driven from both mines simultaneously and was over 3,600m long on completion.

HO1Cs face and Stillingfleet connection to North Selby West 2 Conveyor Road
The early face developments were driven using Dosco Mk2a Revised Hydraulics roadheader setting arch supports with Dosco Mk3 roadheaders driving the lateral roadways. As the mine progressed the face heading development Dosco roadheaders were replaced with BJD flat chain mat continuous miners (Heliminers). Roof bolting replaced the arch supports to achieve faster drivage rates.

BJD (Dresser) Heliminer
Lee Norse LN800 continuous miners gradually replaced the BJD Heliminers and were used from the early 1990s.

Lee Norse LN 800 2TT
Dosco Mk3 roadheaders which were being used to drive the lateral headings at Stillingfleet Mine were gradually replaced with the smaller, more compact Dosco LH 1300 roadheaders.

Dosco LH1300 Roadheader
The coal clearance system at Stillingfleet Mine was designed to have capacity for the coal from North Selby Mine by using a system of bunkers and staple shafts as described below.
A 7.5m diameter, 2000 tonne staple bunker was created in the North Intake near to the pit bottom area called the North Intake Staple Bunker as seen below on the plan.

Plan showing North Intake Staple Bunker at the bottom right of the plan

Stillingfleet No1 and No2 shafts and pit bottom area
As the South Intake progressed a further bunker was created called the Kelfield Bunker as shown below on the plan.

Kelfield Bunker in South Intake conveyor road
At the end of the South Intake the roadway turned to the south west, heading towards the Gascoigne Wood Bunker 6 staple shaft. A bunker and conveyor drive house was created in this south west lateral roadway near to the junction with the South Intake as seen on the plan below. A ventilation connection, already existed from Mar 1987 and this was kept in use with a .8m diameter 20° inclined borehole. A small section, one in one (45)° drift was also created at the end of the lateral to give access and supply air to Gascoigne Wood Mine.

Stillingfleet South Conveyor road and Gascoigne Wood south west lateral connection roadway to Bunker 6
The Gascoigne Wood coal clearance connection roadway to the south of the mine was completed in Dec 1987 to load coal into Gascoigne Wood Mine via a 2000 tonne, 7.5m diameter staple shaft called Bunker 6 as seen on plan below.

Plan of Bunker 6, Ventilation Borehole and 1 in 1 Drift connections to Gascoigne Wood Mine

The Bunker 6 Westerland feeder coal clearance connection from Stillingfleet Mine.
The conveyors in the east and south intake lateral roadways at Stillingfleet Mine had to transport coal from North Selby and Stillingfleet Mines. The drive house roadways were 5m high by 7m wide, square section stanchion girders and were created to house the double, 6.6 K.V. 750kw, steel cord conveyor drives. The drive house was situated in the South Intake roadway near to the pit bottom with the steel cord conveyor running to the south of the mine towards the Gascoigne Wood Mine connection.
Stillingfleet Mine developed the east and west lateral headings to the furthest extent and worked faces from 1988. The west side of the mine worked 12 faces, the last being H219s in 1998 and the east of the mine worked 6 faces, the last being H256s in 1995 very near to the North Selby Mine workings. During this period the north lateral headings were developed and a further north east lateral was driven where 2 faces were worked. As the mine progressed northwards a west and east lateral was developed with 9 faces worked from 1995 to 2002.
An east lateral heading developed was developed at the south side of the mine. Production started in this area in 1995 with H300s face. Eight faces were worked in what was known as the Escrick Brickworks area and finished with H307s in 2004. When this area of the mine was developed a 1000 tonne horizontal bunker was created as storage for surges in production in the east lateral which loaded onto the South Intake steel cord conveyor.
When North Selby and Stillingfleet Mine merged in 1997, reserves became available to be worked from Stillingfleet Mine in the North Selby area. Seven faces were worked in this area, the final face being H853s which finished production in August 2004, one week after H272s.
From production starting in Jan 1988 until closure in August 2004, Stillingfleet Mine worked 49 longwall coal faces, 7 of which were in the original planned area of North Selby Mine. The faces were worked using Anderson Strathclyde AM500, 375 KW D.E.R.D.S shearers with face equipment supplied by Gullick Dobson and Dowty Meco. As the mine progressed, Joy 4LS shearers with Joy face equipment replaced the original equipment on the faces.
Mine plans attribution
Reproduced with the permission of © Intellectual property and copyright 2025 The Mining Remediation Authority. All rights reserved