The first contract for the drift drivages was placed with Cementation Mining on the 15th July 1977 with site work commencing on the 1st of August 1977. The 1 in 4 Drifts were completed using the modified SB 600 Roadheaders setting circular, waterproof, sealed, round section supports. The waterproof seals were installed at 832m and the drift continued for a short distance until the spine tunnel drivages started. Cementation Mining replaced the drift roadheaders with two, heavy duty Dosco Mk 3 Roadheaders. The South Tunnel continued at 1 in 33 incline to the East on to 1670m from the drift portal, setting 17 x 12 feet arches. At this point an erection chamber was created, 35m long, 8.6m high and 6.8m wide. This erection chamber was created to build the Robbins 193-214 Tunnel Boring Machine designed to drive the South Spine Tunnel. The machine construction was started in July 1981 and completed in October 1981. During the construction of the Robbins TBM, the North Spine Tunnel continued at an average rate of 65m to 70m per week using the Dosco Mk 3 roadheader, reaching 2891m when the contract with Cementation Mining was completed in August 1981.

Dosco MK3 Roadheader
The main reason the North Spine Tunnel continued was the urgency of the connection to Wistow Mine for the initial coal clearance. At the completion of the contract with Cementation Mining a new contract was started with Thyssens who took on the drivages, the South Spine using the Robbins 193-214 TBM. Thyssens replaced the Dosco Mk3 Roadheader with a Meco Titan E134 C Roadheader and the North Spine Tunnel continued.

Meco Titan(Paurat) E134 C Roadheader.
When the tunnels reached 3843m the gradient was changed to 1 in 40 North Easterly. When the contract with Thyssens was completed Amalgamated Construction (AMCO) took the next contract and completed the spine tunnels.
Having talked to a mate who worked at Gascoigne Wood for many years I have a list of the ventilation slits, substations and coal clearance bunkers travelling inbye from the Drift bottom. The connecting roadways between the North and South Spine Tunnels were called V Slits up to number 11 then they were called Bunker Slits.
926m- Pumping Station.
V1 – Locomotive Garage and main 6.6kv 185mm Ring main substation.
V2- Ventilation Slit and Substation.
V3- Ventilation Slit and Wistow Mine Staple Bunker
V4- Originally a Wistow Mine single staple bunker but later a North and South Staple with an East and West Westerland feeder conveyor.
V5- Ventilation Slit and a main 6.6kv 185mm Ring main substation.
V6- Offset slit for battery charging station.
7208m- South Spine ventilation shaft to Wistow Mine. (later disused)
V7- Staple shaft to Wistow Mine. (later disused)
V8- North and South staple bunker with access ladders to Wistow Mine.
7916m- Second ventilation shaft to Wistow Mine. 7208m borehole was disused when this was completed.
V10- Ventilation Slit and Locomotive passbye.
V11- Ventilation Slit.
Bunker 5-Ventilation Slit. Temporary bunker to Stillingfleet Mine and main 6.6kv 185mm Ring main substation.
Bunker 6-Stillingfleet and North Selby Mines staple shaft.

The Stillingfleet Bunker in the South Spine with a Westerland weigh feeder loader.
Between Bunker 6 and Bunker 7 was a 200m slit towards Stillingfleet Mine with a coal clearance borehole used until the complex closed.
Bunker 7-Riccall and Whitemoor Mines staple shaft.
Between Bunker 7 and Bunker 8 was the final inbye 6.6kv 185mm Ring main substation.
Bunker 8- Riccall and Whitemoor Mines staple shaft via Westerland variable speed feeder.
At the bottom of Bunker 7 and Bunker 8 Staple shafts the coal was delivered onto a Westerland weigh feeder conveyor onto a conveyor. This conveyor could direct the coal onto either of the north spine cable belt or the south spine ASL conveyors.
At the furthest point of the spine tunnels was the Riccall Mine connection via a 1 in 7 drift. The Gascoigne Wood / Riccall Mine connection had a dedicated 6.6kv supply to the booster fan supplied from Riccall Mine to ventilate Gascoigne Wood. I was on the team installing these fans and switchgear in a very hot area of the mine.
This area of the mine also had a connection via an angled access borehole from Riccall Mine to Gascoigne Wood. This 62m shaft, with ladders, was used for access before the 1 in 7 drift was driven.

The 62m inclined access shaft to Riccall Mine
Inbye of the 1 in 7 Drift, Riccall Mine Connection was the stub heading where the Robbins TBM was driven forward and abandoned

Gascoigne Wood Spine Tunnels at Riccall Connection 1 in 7 Drift .





















