The development of Whitemoor Mine.

© Copyright Ben Brooksbank and licensed for reuse under a cc-by-sa/2.0 Creative Commons Licence.

Whitemoor Mine in 1988

The shafts at Whitemoor were the second deepest in the Selby Coalfield. Number One downcast shaft was 931m and Number Two upcast shaft was 941m deep. During the sinking of the Number Two a European record of 131.2 metres of fully concrete lined shaft was achieved in a month. After completion of shaft sinking in June 1985 the underground infrastructure to develop the mine, pit bottom rope haulage system and coal clearance system was started. Whitemoor was the only satellite mine in the Selby Coalfield to use a rope haulage for transport of equipment and for manriding purposes. This was due to the pit bottoms being deeper than the Barnsley seam. Four, 250m drifts at a 1 in 4 incline were developed by Thyssens mining contractors to access the main lateral roadways in the Barnsley seam. The first two faces to be developed east of the pit bottom were H01Bs which was 200m long and was approximately 800m from the pit bottom and 240m long, H02Bs, 1050m from the pit bottom. Both faces were taken off the East Return Roadway. The faces were worked from South to North. Four lateral roadways were developed to the east of the mine and a single conveyor roadway driven to the west connection with Riccall Mine. The conveyor  roadway had the rope haulage installed for manriding and transport running east and west sides of the mine.

A 6.6kv, 750kw double drive, steel cord conveyor identical to the one installed at Riccall Mine, ran 3000m from the Riccall Connection at the west of the mine to the faces at the east of the mine passing through the pit bottom area. The connection to Riccall Mine South Conveyor Road was  made in November 1986 using a Dosco Mk2A Revised Hydraulics Roadheader with a further connection to the South Return Roadway made in December 1987. An 8m high, 80m long Drive House and a Bunker area were created at the connection for the Whitemoor coal production to start in January 1988. This conveyor loaded onto the Riccall Mine Steel Cord Conveyor.

Plan showing Whitemoor and Riccall Mine Steel Cord connection.

The next face to be worked starting production in 1989 was H621s at the west of the mine. This face loaded straight onto the Riccall Mine Steel Cord Conveyor. H622s and H624s were the next two faces at the west of the mine starting production in 1990 with developments underway at the east of the mine for H615s face which started production in 1991. During the production of  H624s the face hit some faulted areas which created cavities needing remedial work. During the remedial work, the face was shuttered and straw was used as packing along with pumped liquid cement. This system was used to consolidate the face through the faulted areas. Very soon after the use of the straw infill on H624s face, H444s face at the south side of Riccall Mine became affected with mice. The first time it was apparent that we had the thieving rodents was snap wrappings were found torn and food stolen. Eventually the mice were seen all around the workings at Riccall Mine.

Mice were always a problem at the older pits due to ponies being used underground. The associated straw, hay and food usage meant the mice were inadvertently brought underground in these bales of bedding and hay feed bales. We could only assume the same thing happened with the straw packing bales used on H624s face.

Plan showing faces worked at the West of Whitemoor Mine adjacent to Riccall Mine.

In 1991 the face headings were developed for H626s and H623s, the last two faces at the west of Whitemoor Mine. These face were adjacent to the faces worked at the south and south west of Riccall Mine. H623s started production in 1991 with H626s starting production in 1992. The lateral roadway to H626s was extended to the west and made a connection with the Riccall Mine South West Trunk as an intake roadway for the faces worked in that area. H626s finished production in 1993 and production was transferred to the east of the mine.

The east side workings were extremely hot due to the depth of the seam at nearly 1000m. Floor heave and weighting was also a problems as the mine progressed further eastwards.

When the East Conveyor lateral roadways were completed and H615s face was producing coal, the lateral roadways to the north and south for the next phase of developments were started.

The North East Lateral headings were driven 1000m to the north where a junction was created. The headings then developed 2500m towards the eastern limit of planning permission for the next five coal faces starting with H630s in 1993. The faces at this part of the mine used Longwall International face equipment and Joy 390kw 4LS Shearers. H631s started production in 1994 followed by H632s in 1995. These three faces worked from north to south. The next face panel was not worked and the next two faces, H634s and H635s were developed towards the east boundary of the coalfield at the River Derwent working on an east to west orientation. H635s face was the last face at Whitemoor Mine which started production 20th February 1998 and finished production on the 8th June 1998.

The South East Lateral headings were driven 2000m to access the next five coal faces starting with H616s in 1992. This area of the mine used Longwall International face equipment and BJD 300kw Ace shearers with face lengths of 210m. H617s was the next face in production which started in 1993 with H619s, H620s starting production in the next two consecutive years. The coal to the south of H620s was never developed. The last coal face in the south east of the mine was H641s which was worked west to east. This face was 235m in length with face gate length of 1850m. This face started production in 1996 and was completed in 1997.

Whitemoor Mine showing all the faces worked.

All the faces at the east of the mine used roofbolts as primary supports and were developed using JCM 12 Continuous miners. All lateral roadways were developed using 58 tonne, 393kw Dosco LH1300 or Anderson Strathclyde RH22 Roadheaders. Contractors were used to carry out development and salvage work from 1993 with British Coal / RJB Mining workers employed to work the coal faces. Whitemoor Mine achieved it’s weekly record of 64,000 tonnes in February 1993 and produced it’s annual record production of 2,210,000 tonnes of coal in 1994.

During the 10 years of production Whitemoor Mine used diesel and battery free steered vehicles along with diesel and battery locomotives along with the rope haulages to supply the underground equipment and for manriding.   

Transferring; Moving or travelling?

When the Selby Coalfield was ready to be staffed a transfer system was created to ensure the smooth transition of skilled mining men from closing collieries in North Yorkshire. A phased closure programme of pits in Wakefield and Castleford created the first wave of men to move to the new Selby Coalfield started in 1979 and continued in the late 1980s. The men who were asked to stay in the industry from the closing collieries were given options to either travel or move house to the Selby area.

The first option at some of the closing Wakefield collieries was to travel by coach. This mode of transport to the pit had  always been an option around mining areas for a very long time. We called it the Pit Paddy in the Barnsley area and it ran thousands of miners to work every day for decades on the Tracky buses (Yorkshire Traction).

The Selby Mines were a substantial distance from the closing collieries so privately contracted coaches were used instead of the public services buses used previously.      

Another option for the transferring men was to travel in their own cars to the new coalfield. A payment was made for the extra travelling distance, in miles, between your existing Colliery or from your home which ever was the nearest to the new Selby Mine of your choice. This option was very popular due to the flexibility it gave you to work overtime especially on the night shifts. Many men used this option for the life of the coalfield.

The third option available was to up sticks and move house to the Selby area. The criterias were that you had to move to a home within a certain distance from your new pit and that the mortgage or rent at your new house was greater than the amount you were already paying for your old house. The amount you received was up to £48 per week with a further one off payment for resettlement which we called Carpet and Curtain Money. You were paid the mortgage assistance for 5 years. The money paid reduced by 25% for the next 3 years until year eight when it ceased. Some men I knew used this option to rent a house from the new housing association estates to see if they settled in the area. If they decided it wasn’t for them they could move back and restart the travelling allowance again. Hundreds of miners and families moved to Selby into the new houses being built in the villages near to the new mines. Selby, Thorpe Willoughby, Hambleton, Brayton, Barlby, North Duffield, Riccall and Hemingbrough had new housing developments and were all very popular with the mining families. Sherburn in Elmet, Cawood and Wistow were popular with miners transferring to Gascoigne Wood and Wistow Mines as they were sited west of the River Ouse.

One difference between the villages to the East and the West of the River Ouse was there was no mains gas supplies in the East but a big bonus was you had no Selby Toll bridge to contend with on afternoon shift on market day.

Ron Bruce’s memories of the Mines Rescue Station

These are the memories of Ron Bruce, Selby Executive Committee (Estates)

“I have been recalling my memories of the Mines Rescue Station at Selby. The provision of a new rescue station and training facilities were discussed at the Executive Committee Meetings.

There were certain statutory regulations regarding the distance from a rescue facility to a coal mine and the Selby Mine sites were outside the parameters of the Wakefield and Doncaster Rescue Stations at Ings Road, Wakefield and Wheatley Hall Road, Doncaster.
A new facility was required  so a site at Osgodby on the A63 near to the A19 was selected. This site could serve the Selby coalfield and collieries along the eastern edge of existing coalfield around Pontefract and Doncaster.


I was able to negotiate the purchase of some 4 acres which was sufficient for the Rescue Station and associated houses for some of the Rescue Men and families. This facility was very much ‘State of the Art’ when it was completed in the mid 1980’s especially when compared to the Rescue Station on Ings Road at Wakefield.
Shortly after the opening of the new facility and with the closure of the western collieries around Wakefield, the Wakefield Mines Rescue was decommissioned in 1986 and the site was sold for retail development. A ‘Blue Plaque’ visible from Ings Road marks the location of the former station”.

The Selby Mines Rescue station closed after the Selby Complex finished mining in 2004 and rescue facilities were moved to Kellingley Colliery. The Selby Rescue Station site was sold for housing development. The site is straight opposite the Garden Centre on the A63.

The Rescue Station staff travelled between the old Selby site and the new site at Kellingley Colliery until the changes were completed.

Ron Bruce’s memories of acquiring the land

I have been in contact with Ron Bruce, who was part of the Selby Executive Committee. Ron worked in Estates as part of the committee and was in charge of the land acquisition for the Selby Coalfield Project. Below are some of his memories.

The geologists and mining engineers at the North Yorkshire N.C.B. Headquarters always thought that the Barnsley seam was available to the east of the existing coalfield and they were right. When Kellingley Colliery was planned to the East of the existing coalfield in the 1950s, a test boring program for the new mine proved that the Barnsley seam, also known as the Warren House was a workable seam.

Kellingley Colliery never worked the seam as the pit was sunk to work the Silkstone and Beeston seams. Five further boreholes were drilled in the Selby area in the 1960s which proved the existence of the Barnsley seam and the prospects of a new coalfield.

The No.1 Cawood borehole was drilled as part of the Selby Coalfield project in late 1972. This was situated on Ryther Road at Cawood. The contractors for this hole were Cementation Exploration Limited. The small piece of land needed to site the drill rig was 1/5 acre and this land was rented for three months from the farmer, with compensation for crops lasting twelve months. The soil on the site was moved out of the way to create hard standing for the drill rig. When drilling was completed the site was restored back to farm land using the displaced soil. The core sample data was analysed and the results were confirmed on 22 December which proved the Barnsley seam was 10ft 3 inches. A very good start to the project.

Ezra, D. (1976) Coal: Technology for Britain’s future. London: Macmillan (page 99)

Bill Forrest, deputy director (mining) of the North Yorkshire Area of the N.C.B. was in charge of the Selby project. He decided a strategic team was to be created to manage all aspects of the project and was to include Mine Planners, Mining Engineers and Estates. The team was called the Selby Executive Committee. The first job to be carried out was a huge programme of 84 surface boreholes to prove the extent of the seams available for mining. The contractor who carried out this specialist drilling program was Foraky Limited.

Below is the memorial in remembrance to the seven men lost in the Lofthouse Disaster on 21st March 1973. It is very near to the rescue borehole site at the junction of Wrenthorpe Lane and Batley Road.

Gascoigne Wood site was acquired partly from British Rail (the former marshalling yard site) and partly from a local farmer and was initially 164 acres. Further areas were acquired from this farmer when the coal preparation plant was installed lagoon and tipping areas were required.

Wistow site was acquired from a local farmer and fortunately it was on the market at the time. It was the smallest mine site in the coalfield at only 29 acres.

Stillingfleet site was acquired from Escrick Park Estates together with land required for access and improvements to the highway connection to the A19. The site position meant building a new two lane road from the mine site to the Cawood Road junction. The site was 63 acres.

The 100 acre North Selby site was acquired from a local farmer and the whole farm was purchased since the land remaining was not a viable undertaking. The farmer was able to purchase a new farm to the east outside the coalfield area. Land for the two lane access roadway to this site, which was over a mile in length, was acquired from Escrick Park Estates. In addition at North Selby a racehorse stud complex at Chequer Hall was acquired because of possible noise problems during blasting and drilling operations in the development stages. This area together with the balance of the farm land acquired with the shaft site were granted on tenancy to an existing British Coal farm tenant who gave up his tenancy on a small farm at Cleckheaton and moved to Escrick with his Shire Horses. When completed the  North Selby Mine was 80 acres.

Riccall and Whitemoor sites were both acquired from a local farmer under a single purchase and he was able to acquire land to the east outside the coalfield area. Riccall Mine site was 64 acres and Whitemoor Mine site was 67 acres.

During the development of the early underground tunnels of the Selby Mines, Selby District Council decided to charge the N.C.B. rates for the mine roadway development phase due to the coal being extracted during tunnelling. The N.C.B. appealed these rates as the coal was part of the development. This issue was taken to a Lands Tribunal in London and was resolved in favour of the N.C.B.

Continue reading Ron Bruce’s memories of acquiring the land

The Public Inquiry April to June 1975.

A public inquiry allows everyone with anything to say, a forum in which to say it. And there was certainly a lot of people with a lot to say about the plans for the Selby Coalfield. Some were in favour, some were against, and likely, many were undecided.

Some described the plans as the ‘rape of our countryside’, others thought ‘a coalmine will be a goldmine’. Anyway, no matter the side, the 2 April 1975 was when it all began in the Museum Hall on Park Lane, Selby, attracting a great deal of interest from the public. (Ezra, 1976, p114)

An office was rented, which was the N.C.B. public information centre on Finkle Street, Selby. Anyone who had any question about the project could raise issues or get answers to questions raised about the project.

There were representatives at the inquiry from the NCB, from North Yorkshire County Council, Selby District Council, Yorkshire Water Authority, British Railways, The National Farmers Union etc. etc. Each group had its own concerns, the water authority was worried about drainage and potential flooding for instance, and there was a massive concern generally about subsidence.

Mr Eric Orchard, a world expert on subsidence explained that in the past there had been little thought given to the potential damage caused by subsidence; houses had collapsed and fields had flooded. Today though was very different, coal miners were more informed and the whole process was much more scientific. Orchard went on the explain the methods that would be used to control the effects of subsidence and reassured the inquiry that there would be very little damage. Any repairs would be minimal and the NCB would pay for them.

Orchard’s reassurance went so far but didn’t 100% calm the worry around all the medieval churches and historic buildings. However, the NCB with its duty of care to these buildings, believed that the systems planned for mining the coal would protect the churches and similar important buildings.

But what about Selby Abbey? The risk was too great. An architect looked into the details of the Abbey’s foundations and found that any changes in the water table levels (something that could happen with mining) would threaten the structure of the Abbey. The NCB agreed to leave a pillar of coal underneath the Abbey as support but the size of the pillar was under question too. Selby Council was worried about the sewers which could crack if subsidence occurred, they were also concerned about industrial buildings and schools and hospitals so they wanted a larger supporting pillar, not just underneath the Abbey but under the whole town.

A larger support, the NCB argued would lose them nearly £100 million in lost coal. so it was left to the Government to make the final decision on the size of the Selby pillar.

Local people, especially farmers, had their own worries, flooding being a top concern. One farmer thought that the NCB could turn ‘an agricultural area into a duckpond’. The NCB didn’t deny that there could be adverse effects but agreed to put right any damage and to pay compensation to those effected. (Ezra, 1976, p121)

There were ordinary home owners too who were concerned about damage to their properties. The NCB agreed that in the event of damage they would decide whether to repair or compensate but said that severe cases were unlikely.

There were more issues raised; naturalists were concerned about delicate ecosystems; residents were concerned about heavy lorry traffic; there were unpopular changes planned to reroute the railway line, the winding towers were going to be taller than expected and be a blot on the landscape, there were anxieties about massive migration of workers to the mines and the labour force depletion from other areas. All agreed that mining ‘ghettoes’ were to be avoided. Two village councils even refused to have a mine named after the local village hence Whitemoor Mine and North Selby Mines.

The inquiry lasted for thirty eight working days. The Secretary of State gave his permission on 1 April 1976, a year after the opening of the inquiry, and even though not everyone was pleased about it, there was a feeling that Selby should see the best in it and make it a successful venture. One of his conditions was that pillars of coal must be left under central Selby.

Ezra, D. (1976) Coal: Technology for Britain’s future. London: Macmillan.

‘Dash for Gas’

In the years following the 1974 Plan for Coal and the implementation of the need for consistent energy supply, to be based on continuing coal usage, a further plan was being devised by the Conservative Party. This involved privatisation of the energy generation and supply followed by the privatisation of the coal industry. The twelve electricity utility companies were privatised in 1990 and became two huge companies called Power Gen and National Power. The nuclear industry was removed and was kept under state ownership until 1995 where it was merged with Scottish Nuclear to become British Energy. In 1991 the Scottish energy generator became Scottish Power and Scottish and Southern Electricity.

Up to 1990 the generation of energy from gas was not allowed but in 1992 this changed when the restriction was removed allowing the generators to use the the North Sea Gas reserves. This resulted in a huge increase in gas generation called the ‘Dash for Gas’. At privatisation in 1990 the fossil fuels used for generation of base load was 92% coal, 7% Oil and 1% gas. The UK coal used for generation was over 73 million tonnes in 1990. The newly privatised energy industry signed contracts with British Coal to supply 65 million tonnes of coal up to 1993. Due to the impending loss of coal market with the new energy producers, the government minister Michael Heseltine announced a closure plan of 31 mines with three pits being left out of the announcement. One of the mines was Whitemoor in the Selby Coalfield.

This left 19 mines ready for the privatisation of the industry planned for 1994. After 1993 coal contracts with the two new energy companies reduced to 35 million of UK produced coal. Due to the huge building program of Combined Cycle Gas Turbine power stations, the import of cheaper, often subsidised coal from Russia, orimulsion and petcoke from the U.S. the writing was on the wall for the coal industry and the closure of coal fired power stations was the obvious next step.

The closure of the 31 coal mines with the loss of 37,000 miners in 1993 and the perceived concern over the potential closure of the Selby Coalfield had a fundamental effect on the staff with a daily shout in the pit head baths of ‘Have you heard owt’ meaning when are we closing. Mining contractors became more commonplace for even small jobs and staff changes were happening as the men from the closing pits saw Selby as the place to be for at least a few years anyway and staff leaving due to the mistrust of the new owners, RJB Mining.

The Selby Coalfield reached full production in 1992/93 with an output of 10.8 million tonnes. The following year, 1993/94, the production peaked at 12.1 million tonnes. the next 4 years were 8.2 million (9 months), 11.4 million, 10.3 million and 8.5 million tonnes respectively. In 1997, the merger of North Selby and Stillingfleet Mine along with closure of Whitemoor Mine was announced. RJB Mining took a very risk averse strategy on production faces from 1995 onwards. In 1997, the developments at the South West and the North East of the mine were abandoned at Riccall Mine with long life developments ceasing at Wistow and Stillingfleet Mines. Due to the closure of Whitemoor and North Selby Mines the number of faces being worked dropped and therefore output from the complex fell to 7.14 million tonnes. The original concept of the coalfield was to produce 10 million tonnes of coal from five mines. The closure of 2 mines and subsequent planned loss of production ensured the complex could never run at a profit due to the standing cost of Gascoigne Wood Mine. At the end of 1997 an announcement was made at Riccall Mine that the complex had a maximum of 7 years production left if we were lucky. All the readily available coal faces in the Selby Coalfield were worked along with a new development to work 9 million tonnes of Stanley Main coal at Riccall Mine to honour the coal contracts up to 2004 and the closure of the coalfield. In the year of closure the coal produced in the UK was down to 13 million tonnes per year, a figure the Selby Coalfield alone had almost achieved in 1994.

List of Coal Faces at Stillingfleet Mine

Plan of coal faces at Stillingfleet Mine with seven worked in the North Selby Mine area.

The first coal faces at Stillingfleet Mine were worked from the east / west lateral roadways. The first face worked in Jan 1988 was H01Bs on the west side of the mine. H01Cs started production in May 1988 at the east side of the mine. The lateral heading to the east of the mine was the connection with the North Selby Mine lateral conveyor roadway called West 2 and was completed in July 1989. The heading was driven by two Dosco Mk 3 roadheaders with heading being driven from both mines simultaneously and was over 3,600m long on completion.

The early face developments were driven using Dosco Mk2a Revised Hydraulics roadheader setting arch supports with Dosco Mk3 roadheaders driving the lateral roadways. As the mine progressed the face heading development roadheaders were replaced with BJD flat chain mat continuous miners (Heliminers) and roof bolting replaced the arch supports to achieve faster drivage rates.

BJD (Dresser) Heliminer

Lee Norse LN800 continuous miners were also used in the  mid 1990s.

 

Lee Norse LN 800 2TT

Dosco LH1300 roadheaders were used for the lateral roadways to replace the Dosco Mk3 roadheaders. 

The Gascoigne Wood coal clearance connection roadway to the south of the mine was completed in Dec 1987 to load coal into Gascoigne Wood Mine via a 2000 tonne, 7.5m diameter staple shaft called Bunker 6. A 7.5m diameter, 2000 tonne staple bunker was created in the North Intake near to the pit bottom area called the Kelfield Bunker and a bunker was created in the south west lateral towards the Bunker six staple bunker. A ventilation connection already existed from Mar 1987 and this was kept in use with a .8m diameter borehole. A one in one (45)° drift was created at the end of the lateral to give access to Gascoigne Wood Mine.

Plan of Bunker 6, Ventilation Borehole and 1 in 1 Drift Connections to Gascoigne Wood Mine

The Bunker 6 Westerland feeder coal clearance connection from Stillingfleet Mine.

The conveyors in the east and south lateral roadways at Stillingfleet Mine had to transport coal from North Selby and Stillingfleet Mines. Roadways in the drive house areas of 5m high by 7m wide, square section stanchion girders were created to house the double, 6.6 K.V. 750kw, steel cord conveyor drives. The Drive House was situated at the of the south Intake roadway near to the pit bottom which loaded onto a lower lateral roadway which delivered via a 2000 tonne staple shaft into the Gascoigne Wood Spine Tunnels.

Stillingfleet Mine developed the east and west lateral headings to the furthest extent and worked faces from 1988. The west side of the mine worked 12 faces, the last being H219s in 1998 and the east of the mine worked 6 faces, the last being H256s in 1995 very near to the North Selby Mine workings. During this period the north lateral headings were developed and a further north east lateral was driven where 2 faces were worked. As the mine progressed northwards a west and east lateral was developed with 9 faces worked from 1995 to 2002.

The South side of the mine had east lateral heading developed and started production in 1995 with H300s and finished with H307s in 2004.

When North Selby and Stillingfleet Mine merged in 1997, reserves became available to be worked from Stillingfleet Mine in the North Selby area. Seven faces were worked in this area, the final face being H853s which finished production in August 2004, one week after H272s.

From production starting in Jan 1988 until closure in August 2004, Stillingfleet Mine worked 49 longwall coal faces, 7 of which were in the original planned area of North Selby Mine. The faces were worked using Anderson Strathclyde AM500, 375 KW D.E.R.D.S shearers with face equipment supplied by Gullick Dobson and Dowty Meco. As the mine progressed, Joy 4LS shearers with Joy face equipment replaced the original equipment on the faces.

Stanley Main Seam Drifts.

Stanley Main Drifts showing Pit Bottom area, West and East developments of the mine.

Stanley Main Drifts when completed.

During late 1997 a series of canteen meetings with the staff were called at Riccall Mine. An  announcement was made that Whitemoor Mine and Riccall Mine were to become a combined mine and that Whitemoor was to be closed in 1998 when the last face was worked out. We were also told by the manager that Riccall Mine would produce coal for seven more years if we were lucky. Riccall men were told that they had options to either stay at Riccall Mine until closure, apply for redundancy, transfer to Wistow Mine or go to Whitemoor Mine to work the last face, which was H635s and then be redundant. These options gave the chance for any Whitemoor men to transfer to Riccall.

Rumours were rife from 1992 that the Selby Coalfield was under threat of closure due to diminishing coal contracts with the two newly privatised energy generators but to be actually told was a surprise as we had achieved exceptional production figures for many years. The announcement was also made that Riccall Mine was to develop drifts up into the 2.5 m thick Stanley Main seam for the last few years of production which was another big suprise as the Selby Coalfield had planning permission for the Barnsley Seam only.

The application for planning permission to work the seam was presented to North Yorkshire County Council in mid 1998 and was passed in July 1998 without major objections. The permission was to mine 9 million tonnes of Stanley Main Coal. Permission was also granted in 1999 to tip the waste from the Stanley Main Drift developments at the Gascoigne Wood tipping site.    

The Stanley Main Drifts junctions were 250m from the pit bottoms in the North Intake and North Return roadways. Skanska were chosen as the contractors for the work to be carried out. The first drift to start was the Intake which started development in early 1999. The junction was created with a Boart Multi Drill Rig using boring and firing. The drift progressed on an upward North East incline at 1 in 16.  

When the Intake Drift had reached 70m a junction was created. The Boart Drill rig then turned to the East and drove an 80m heading at 1 in 23 on an uphill incline. The junction for the Return Drift was created in August 1999 and the Boart Drill rig then drove back South West at 1 in 20 downhill to create the circuit to the North Return which was completed in early 2000

The Intake Drift was developed with a Paurat Titan E134b Roadheader using heavy duty arch supports. 

The development of the Intake Drift from the cross slit started in May 1999 and drove at an incline of 1 in 12 uphill. It passed through the Dull Seam, Kent Thick seams and the Kents Thin Seam reaching the Stanley Main Seam in late Dec 1999.

The Return Drift was started in September 1999 and was driven by a smaller Paurat Titan E169. The heading progressed well at 1 in 20 on an uphill incline and reached the Stanley Main Seam in April 2000. When the junctions for the Stanley Main Intake and Return Lateral headings were made a roadway was driven west from the Intake lateral junction back towards the North Conveyor Road. A borehole was made for the Stanley Main coal to load onto the North Steel Cord Conveyor from the Stanley Main level.

The Paurat Titan E134b and E169b Roadheaders were made under licence by Dowty. Below are a couple of information sheets for the machines very similar to the machines used in the Stanley Main Drift headings.

 

Information for the post was provided by Phil Wright, Ian Steele, ( Steely ) who worked for Skanska in the Stanley Main Drifts and Kevin Grant, S.C.E. at Riccall Mine.

Mines Rescue Practices.

As part of ongoing training, to ensure competency, part-time Rescue Men had to attend a training session every two months. The training sessions were called Rescue Practices and were programmed so that every part-time rescue worker used the S.E.F.A. breathing apparatus 6 times per year.

S.E.F.A. Closed circuit oxygen Breathing Apparatus.

If a practice was missed due to holidays, illness or injury it was reprogrammed as soon as practicable to ensure competency. The training sessions were usually programmed so that the teams at each pit trained together.

One of the training sessions every year was the Selby Group Competition which included a rescue scenario and a question and answer oral exam.

Rescue competition log entry.

Due to the revision of training after the Lofthouse Colliery disaster in March 1973 a training session working in water was added and had to be carried out every 2 years. This practice involved moving around a swimming pool as a team with diving weights around your waist, and a black bag covering your helmet and facemask to ensure sensory deprivation.

The practice was designed to see what working in teams in slurry and deep water up to 10 feet in depth felt like.

Disorientation and breathing difficulty due to pressure in deep water were issues on this practice. Working under water would only ever be used to save life at a incident.

In Water Training notes.

Using Breathing Apparatus in extreme heat and humidity is very stressful when working in an incident underground. Every 2 years rescue teams were tested in the Rescue Station Hot and Humid chamber to ensure awareness of the dangers of working at physical and mental limits. The S.E.F.A breathing apparatus were set to high oxygen flow for this training session. The teams were set a training scenario early in the session. The teams then entered the chamber for the last 19 minutes at maximum temperature and humidity. The Captain of the team monitored the atmospheric  conditions inside the chamber using a piece of kit called a Whirling Hygrometer and saturation / heat chart.

Whirling Hygrometer.

Photograph courtesy of Science Museum.

Temperature / Saturation working time chart

Continual physical checks ensured the team’s safety whilst the men carried out heavy exercise consisting of either riding a static cycle, shovelling piles of gravel, carrying water barrels or lifting weights in rotation. The men were very closely monitored for signs of heat stroke and exhaustion.

Training log entry for hot and humid practice.

Rescue men attended practices at collieries in the Rescue Station area to familiarise themselves with the location of all the other pits they may be called to in the case of an incident.

On arrival at a practice the Captain and the team were given a brief on the rescue scenario along with the mine plans needed. They checked and tested all the equipment likely to be needed and progressed to the Fresh Air Base. The pits in the Selby Rescue Station area were Gascoigne Wood, Wistow, Stillingfleet, North Selby, Riccall, Whitemoor, Kellingley, Hatfield Main, Thorne, Prince of Wales and Hayroyds Colliery.

Below are some of the Rescue Practices I attended at different collieries.

 

Practice at Hayroyds Colliery.

Practice at Thorne Colliery.

Practice at North Selby Mine.

Practice at Whitemoor Mine.

Practice at Wistow Mine.

Practice at Riccall Mine.

Practice at Kellingley Colliery.

The above Rescue Practices are some of the entries from my training log. These show the types of scenarios and some of the collieries visited to familiarise the teams. The Rescue Practices were designed to test the teams in very difficult conditions and over a 12 month period all the rescue equipment available for use is used as part of these training scenarios. 

Many thanks to Katie Cavanagh and Stephanie Thompson at the National Coal Mining Museum for making my training logs available.

Gascoigne Wood Washery Plant.

During the early stages of development and planning of the Selby Coalfield, a huge project was undertaken to prove the available seams were workable. Nearly 90 boreholes and 345 in seam seismic surveys were carried out to prove the available coal. The planning permission was based on the findings which proved 2 billion tonnes of available reserves of which 600 million tonnes were the Barnsley Seam. The comment made at this stage of planning was the Barnsley Seam is clean coal, good enough to send straight to the power station and that the 600 million tonnes were relatively dirt free reserves.

Gascoigne Wood mine was designed to have no coal preparation facilities or tipping space but due to underground faulting, dinting, sinking of cross measure drift and face conditions across the complex the amount of dirt in the coal was becoming a problem. The decision was made in the early 1990s to build a huge screening and coal preparation plant on site. The existing covered coal storage facility was chosen to house all the equipment needed to build the new preparation plant.

The coal storage was redirected to an adjacent open area that could store up to 400,000 tonnes of coal; which is over two months’ production. The new stocking ground had coal stackers with boom conveyors capable of raising, lowering and rotating to ensure the coal was stacked efficiently. Each stacker could process around 3,500 tonnes of coal per hour with the whole system mounted on a transportable carriage rather like an overhead crane. The coal was reclaimed from the storage area, to be processed, using a rotating barrel incorporating a reclaiming bucket. This system operated at 1500 tonnes per hour and sent the coal to the preparation plant inside the old storage area.

The Original Covered Coal Storage Area

The Boom Stacker and Reclaimer System

Gascoigne Wood site showing coal preparation facilities.

The coal preparation plant contained inside the old storage consisted of 4 screens manufactured by Don Valley Engineering. These were known by their nickname ‘banana screens’ due to their curved design. Two screens were used in each route from the drifts and were capable of processing 900 tonnes per hour at a size of 1 inch. The coal was then blended with smaller coal from the 16x flip flow IFE screens. The coal washing system was 6x Parnaby barrel type natural medium with a capacity of 1200 tonnes per hour. The smaller coal was washed using cyclones to deal with the slurry filtration.

Click on the link to show the plant in October 2004 during the last days when the only production in the complex was from SM 504s at Riccall Mine. It gives you an idea how vast and complex the coal preparation plant was.

Due to the site not having planning permission to tip waste and a ban on road haulage transportation, the dirt from the preparation plant was sent to Allerton Bywater Colliery for tipping via railway. Liquid slurry was sent to Wheldale Colliery via an overland pipeline for disposal in the shafts. Coarse waste was sent via railway to Welbeck Site, near Normanton to be used for landfill and reclamation.

When the closure of Allerton Bywater Colliery was announced in March 1992 the need for tipping space at Gascoigne Wood site became a major priority. Planning permission was applied for in July 1993. A full review was carried out on the 133.8 hectare farm land site. At the time, 98% of the land was used for agricultural production with grade 3b moderate soil types covering 79% of the site. Planning was granted in late 1993 to start a 340 acre tip to the East of the mine site. The tip was started in 1994 with precise planning and environmental conditions imposed. As the tip progressed in a modular manner, called cells, continuous restoration took place. 110,000 trees were planted in an 10 metre wide border around the site in the first year with a further 50,000 to be planted as the restoration of the site progressed. Topsoil was added to the site on completed sections within 18 months of completion of each phase.

Gascoigne Wood tip looking south.

Gascoigne Wood tip looking south east.

Gascoigne Wood tip looking north west.

The original planning permission was for an area of 340 acres. Further planning permission was added as the tip was completed with a further extension added to the north and east of the existing one. In 1999 a further planning permission was granted to allow the tipping of waste from the Stanley Main Drifts being developed at Riccall Mine.  

Due to the very high standard of restoration work carried out on the site, Gascoigne Wood Mine was awarded the accolade of ISO 14001, the first mine in Europe to be awarded the International Environmental Standard.

The tip is not recognisable as a Colliery tip now, with vast areas of grass and trees. If you enter ‘Gascoigne Wood’ into Google Earth you can see the extent and standard of the remediation work carried out.

Bibliography

DOWNES, E. (2016). YORKSHIRE COLLIERIES 1947-1994.

Photographs kindly provided by N. Rowley.