Setting up structures and systems for the management of a multi billion pound project such as the Selby Coalfield was a very complex task. After buying the land for the sites of the five satellite mines and Gascoigne Wood, which was the largest site with two surface drifts, coal handling plant and railway loading facilities, a team of surveyors, which is a statutory role at a mine and surveying staff were needed at each site. They were managed from North Yorkshire Area H.Q. at Allerton Bywater.
The first two pits to be sunk were Gascoigne Wood and Wistow Mines. Gascoigne Wood drift tunnelling started in March 1978, Wistow No2 shaft sinking started Jan 1978 and Wistow No1 started in June 1978. As you can imagine a huge amount of surveying preparatory work was carried out on the sites before any sort of construction could take place.
Initially the surveying of the sites were organised from North Yorkshire Area H.Q. where the Selby Coalfield Project Team was set up. Two surveying teams were created called East Side to survey North Selby, Riccall and Whitemoor mines and the West Side to survey Gascoigne Wood, Wistow and Stillingfleet mines. Each team had a surveyor, assistant surveyor and a linesman team. The head surveyor for the Selby Project was Tony Shirley and deputy surveyor Dennis Aitchison.
As the site construction progressed and the sinking of the two shafts on each site were under way, the workload increased massively.
The teams at each mine were created and included a unit surveyor and two assistant surveyors. These posts were advertised nationally in the NCB as new roles open for promotions of existing members of staff as were the management roles within the complex. A team of linesmen and support staff were transferred from closing collieries. Surveying offices were also built on each site.
The teams were created in the following order:
1. Gascoigne Wood 2. Wistow 3. Stillingfleet 4. Riccall 5. Whitemoor 6. North Selby
When the surveying teams at each of the six individual mines were created the East and West Side teams responsibilities were handed over to the new teams at each mine as the site development progressed. The Selby Project team was wound down in 1984.
Tony Shirley, who had been surveyor in charge of the Selby Project was promoted to North Yorkshire Area chief surveyor and the existing chief surveyor, Eddie Garner retired.
Many thanks to Dave Wilson who provided his time and the information in this post. Dave did his training to be a surveyor at Rothwell Colliery and applied as an assistant surveyor working under unit surveyor Jack Donachie at Stillingfleet Mine. He started in 1984 and was later promoted to deputy surveyor. He worked at Stillingfleet until 2003. He worked in outside industry and returned to mining at U.K. Coal at Howarth Park in the planning department in 2008. As the industry wound down he transferred to Kellingley Colliery as mine planner until closure in Dec 2015. He now works at The Mining Remediation Authority.