
Plan of coal faces at Stillingfleet Mine with seven worked in the North Selby Mine area.

The first coal faces at Stillingfleet Mine were worked from the east / west lateral roadways. The first face worked in Jan 1988 was H01Bs on the west side of the mine. H01Cs started production in May 1988 at the east side of the mine. The lateral heading to the east of the mine was the connection with the North Selby Mine lateral conveyor roadway called West 2 and was completed in July 1989. The heading was driven by two Dosco Mk 3 roadheaders with heading being driven from both mines simultaneously and was over 3,600m long on completion.
The early face developments were driven using Dosco Mk2a Revised Hydraulics roadheader setting arch supports with Dosco Mk3 roadheaders driving the lateral roadways. As the mine progressed the face heading development roadheaders were replaced with BJD flat chain mat continuous miners (Heliminers) and roof bolting replaced the arch supports to achieve faster drivage rates. Lee Norse LN800 continuous miners were also used in the mid 1990s.
Dosco LH1300 roadheaders were used for the lateral roadways to replace the Dosco Mk3 roadheaders.
The Gascoigne Wood coal clearance connection roadway to the south of the mine was completed in Dec 1987 to load coal into Gascoigne Wood Mine, via a 2000 tonne, 7.5m diameter staple shaft called Bunker 6. A ventilation connection already existed from Mar 1987 and this was kept in use with a .8m diameter borehole.

Plan of Bunker 6 and Ventilation Borehole Connections to Gascoigne Wood Mine

The Bunker 6 Westerland feeder coal clearance connection from Stillingfleet Mine.
The conveyors in the east and south lateral roadways at Stillingfleet Mine had to transport coal from North Selby and Stillingfleet Mines. Roadways in the drive house areas of 5m high by 7m wide, square section stanchion girders were created to house the double, 6.6 K.V. 750kw, steel cord conveyor drives. The South Drive House was situated at the furthest point of the south lateral roadway which loaded onto a lower lateral roadway which delivered via a 2000 tonne staple shaft into the Gascoigne Wood Spine Tunnels.
Stillingfleet Mine developed the east and west lateral headings to the furthest extent and worked faces from 1988. The west side of the mine worked 12 faces, the last being H219s in 1998 and the east of the mine worked 6 faces, the last being H256s in 1995 very near to the North Selby Mine workings. During this period the north lateral headings were developed and a further north east lateral was driven where 2 faces were worked. As the mine progressed northwards a west and east lateral was developed with 9 faces worked from 1995 to 2002.
The South side of the mine had east lateral heading developed and started production in 1995 with H300s and finished with H307s in 2004.
When North Selby and Stillingfleet Mine merged in 1997, reserves became available to be worked from Stillingfleet Mine in the North Selby area. Seven faces were worked in this area, the final face being H853s which finished production in August 2004, one week after H272s.
From production starting in Jan 1988 until closure in August 2004, Stillingfleet Mine worked 49 longwall coal faces, 7 of which were in the original planned area of North Selby Mine. The faces were worked using Anderson Strathclyde AM500, 375 KW D.E.R.D.S shearers with face equipment supplied by Gullick Dobson and Dowty Meco. As the mine progressed, Joy 4LS shearers with Joy face equipment replaced the original equipment on the faces.

















