


The faces worked at North Selby Mine at the North and South West of the mine.
As you can see from the plan, the faces marked were taken when North Selby was a stand alone mine before the merger with Stillingfleet Mine. Nine faces were mined at North Selby in this area. Four coal faces are shown, but not marked, as they were developed at a later date working from Stillingfleet Mine.

The faces taken at North Selby Mine at the South East of the mine.
As you can see from the plan seven faces were mined at North Selby in this area. One face is unmarked as it was worked from Stillingfleet Mine at a later date. This area of the mine was very hot with heat exhaustion being a major problem due to the working depth of 1100m.
North Selby Mine and Stillingfleet Mine merged in July 1997 but in its short life of 7 years, 16 coal faces were mined. The first face started in November 1990 at North Selby which was H801s.

It was the first face in the country to have a remote face support pump system and supplied the face at 4,500 psi. North Selby Mine was also the first mine in the UK to both develop and use load centres instead of individual gate end boxes to supply the coalface equipment.
On the nightshift of 6th December 1992, North Selby H903s coalface, using an AM 500 DERDS coal cutter sheared 5055m of coal (3.14 miles). This was a European record and along with Thoresby Mine the first time 3 miles of cutting was achieved in a single shift.
The face headings were developed using Lee Norse LN800 Continuous miner. The lateral roadways were developed using Dosco LH 1300 roadheader machines with a Dosco MK3 roadheader driving the west connection to Stillingfleet Mine. As happened at Whitemoor Mine, the heading developments were taken by mining contractors with British Coal/ RJB Mining teams working the coalfaces from 1993.
The faces were equipped with Anderson Strathclyde 375 kw AM500 DERDS or 375kw Joy 4LS DERDS shearers. The face equipment was initially Gullick Dobson and Dowty Meco. Due to mergers of mining equipment suppliers in 1994, Longwall International equipment was used.


